Progress of work on the extension of Piaseczno 22/11 kV substation

In February construction of a new technological building were continued, in the area of:
– roof’s steel construction installation,
– making vertical insulation of a building with mineral wool.
It is planned to complete the roof and vertical insulation next month, as well as start finishing works and installation works inside the building.

More information: www.stacjapiaseczno.pl